Content on this page requires a newer version of Adobe Flash Player.

Get Adobe Flash player

Projects > W.A. Parish Peaker Project – Houston, TX

W.A. Parish Peaker Project – Houston, TX

138kV Switchyard and Transmission Line

Year Completed: 2013

Construction Cost: $5,000,000

NRG

In late summer 2012, Dashiell accepted a project with an aggressive project schedule to design and build a 138 kV generator interconnect substation and a 138 kV interconnecting transmission line for a new peaking power plant being built by NRG at the W.A. Parish power plant near Richmond, Texas. Although the facilities themselves were not technically difficult to design and build, the number of interfaces between existing NRG facilities, the new peaking power plant and Centerpoint created a number of challenges for the project team.

On Thursday, June 6th, Dashiell successfully energized the interconnect substation bus by re-energizing the transmission line from the Centerpoint substation to the NRG W.A. Parish Unit #7 Standby Transformers. On Friday, June 7th, the interconnect breaker to the new generation facility was closed, energizing the transmission line and back-feeding the new power plant through the Generator Step Up Transformer. Even with all of the interface issues that challenged our energization, Dashiell completed this project a full week ahead of our commitment to the customer.