Project Details

Completion Date: 2019

Location: Louisiana

EPC Scope:

  • (1) – 500kV 3 breaker ring switching station
  • (1) – 500kV Transmission Line – 6 miles
  • (1) – 500/230kV Switching Station
  • (3) – 230kV Lines – Greenfield/Rebuild – 23 miles
  • (5) – 230kV Substation Expansions/Modifications
  • (1) – 230kV River Crossing Demo/Rebuild – Including Explosive Demolition

Related Projects

2020
138kV Breaker and a Half SWYD

Engineering and Construction Services: Four (4) Bays Five (5) Lines Coming In and Out Included Current Limiting Reactors

View Project
2017 - Present
115kV, 230kV, and 345kV Projects

EPC Scopes: (2) – 345kV 3 breaker ring SWYD expandable to a future BAAH (1) – 115kV 3 Bay BAAH SWYD (1) – 115kV 3...

View Project
2013
W.A. Parish Peaker Project

138kV Switchyard and Transmission Line

View Project