W.A. Parish Peaker Project

See All Projects
Project Details

Completion Date: 2013

Location: Houston, TX

Client: NRG

In late summer 2012, Dashiell accepted a project with an aggressive project schedule to design and build a 138 kV generator interconnect substation and a 138 kV interconnecting transmission line for a new peaking power plant being built by NRG at the W.A. Parish power plant near Richmond, Texas. Although the facilities themselves were not technically difficult to design and build, the number of interfaces between existing NRG facilities, the new peaking power plant and Centerpoint created a number of challenges for the project team.

On Thursday, June 6th, Dashiell successfully energized the interconnect substation bus by re-energizing the transmission line from the Centerpoint substation to the NRG W.A. Parish Unit #7 Standby Transformers. On Friday, June 7th, the interconnect breaker to the new generation facility was closed, energizing the transmission line and back-feeding the new power plant through the Generator Step Up Transformer. Even with all of the interface issues that challenged our energization, Dashiell completed this project a full week ahead of our commitment to the customer.

 

 

Related Projects

2020
138kV Breaker and a Half SWYD

Engineering and Construction Services: Four (4) Bays Five (5) Lines Coming In and Out Included Current Limiting Reactors

View Project
2017 - Present
115kV, 230kV, and 345kV Projects

EPC Scopes: (2) – 345kV 3 breaker ring SWYD expandable to a future BAAH (1) – 115kV 3 Bay BAAH SWYD (1) – 115kV 3...

View Project
2019
Lake Charles Transmission Project

EPC Scope: (1) – 500kV 3 breaker ring switching station (1) – 500kV Transmission Line – 6 miles (1) – 500/230kV Switching Station (3) –...

View Project
Back to Top